Client
Fondation Berthe Bonna-Rapin (Hospice Général)
Project description
Developing and building 10 Minergie housing buildings in the Development Zone 3.
Scope of services
-
Project management & client representation and defense.
-
Offer regular analysis and strategic advice to optimise the project’s characteristics. Organise building permits and planning.
-
Assistance in resolving land issues and coordinating other partners.
-
Organising mandates for the pools of agents.
-
Monitoring documentation in regards to building authorisation, as well as procedures and negotiations with the OCLPF.
-
Administrative, legal, contractual, financial and technical management.
-
Incorporating and piloting the ‘ad hoc’ general contractor for the construction of the ZDPPE buildings. Managing relations with buyers and monitoring orders.
-
Offer regular progress reports for the Board.
-
Reception and closing of accounts on behalf of the client.
LOCATION
Camino de Santiago, Grand-Lancy
SURFACES
Phase 1: 23,588 m2 SBP
Phase 2: 17,271 m2 SBP
NUMBER OF RESIDENTIAL UNITS
Category ZDPPE : 48 (step 1) + 39 (étape 2)
Category ZDLOC : 106 (step 1)
Category HM : 42 (step 1) + 140 (step 2)
Total (steps 1 et 2) : 375
COST
Phase 1: CHF 98.7 million
Phase 2: CHF 79.3 million
DURATION
Phase 1: 2010 – 2014
Phase 2: 2013 – 2017
PROJECT OWNER
Daniele Grasso